
Prayagraj,
26 March (HS): NCR has achieved another major milestone in its efforts to
strengthen North Central Railway's infrastructure and ensure enhanced speed and
safety in rail operations. The rehabilitation of two major old steel girder
bridges—Bridge No. 48 and Bridge No. 46—located on the Chopan-Chunar rail
section has been successfully completed.
Bridge No.
48: Elevated from ORN-2 Category; Work Completed in Record Time: Constructed
in 1953, Bridge No. 48 (comprising 8 spans)—which had been categorized as ORN-2
due to its dilapidated condition (specifically, bent girder stiffeners and
corrosion)—has now been completely transformed into a new and modern structure.
It is pertinent to note that, within Indian Railways, the term ORN-2 refers to
Category II bridge structures identified during inspections as requiring either
maintenance or rehabilitation.
As part of
this project, the old Broad Gauge Main Line (BGML) loading girders were removed
and replaced with modern 25-ton welded steel plate girders and H-beam steel
sleepers. Additionally, the bridge's sub-structure (piers) underwent concrete
jacketing, thereby significantly enhancing both its service life and
load-bearing capacity. This entire undertaking was executed through a special
drive conducted between March 12 and March 20, 2026, during which all 8 spans
were successfully replaced in record time.
Bridge No.
46: Modern Transformation of a 1953 Structure: Continuing the initiative, the
renovation of Bridge No. 46—a 06-span structure located within the
Chunar-Chopan section—was successfully completed in February 2026. This bridge,
too, was based on outdated standards from 1953, necessitating speed
restrictions for trains crossing it. Now, however, 25-ton welded steel girders
have been installed on this bridge as well, making it suitable for future heavy
freight trains and high-speed passenger trains.
Previously,
a permanent speed restriction of 30 kilometers per hour was imposed on these
bridges for safety reasons; this restriction will now be lifted. This will lead
to improved punctuality for trains. The installation of modern girders with a
25-ton loading capacity will facilitate the smooth operation of heavy freight
trains, thereby boosting the railway's revenue and logistical capabilities. Due
to modern steel sleepers and jacketing technology, the structural integrity of
these bridges now aligns with international safety standards. With the
completion of these works, the Prayagraj Division is now entirely free of
bridges classified under ORN-2 (a category requiring critical repairs).
This
achievement underscores the Ministry of Railways' commitment to 'Mission
Raftar' and the modernization of infrastructure. General Manager Naresh Pal
Singh has commended the team of engineers and workers who successfully
completed this complex task safely and within the stipulated timeframe. General
Manager Naresh Pal Singh specifically lauded the Bridge Line and Engineering
teams, as well as the staff of North Central Railway. This project was executed
under the guidance of Divisional Railway Manager Rajneesh Agarwal by Deputy Chief
Bridge Engineer I.P.S. Yadav and his team, with the active cooperation of
officials and staff from the Division's Engineering and Operations departments.
Hindusthan Samachar / Abhishek Awasthi