Nepal Moves to Grant One-Year Extension to MCC Projects, Authorises Finance Ministry to Seek Approval
Kathmandu, November 29 (HS): The Nepal government has approved a move to grant up to a one-year extension to projects being implemented under the US Millennium Challenge Corporation (MCC) Compact, authorising the Ministry of Finance to take the pro
Representative Image


Kathmandu, November 29 (HS): The Nepal government has approved a move to grant up to a one-year extension to projects being implemented under the US Millennium Challenge Corporation (MCC) Compact, authorising the Ministry of Finance to take the process forward.

A Cabinet meeting has authorised the Ministry of Finance to extend the project timeline by a maximum of one year, provided the extension does not lead to an increase in project costs.

According to the Ministry of Finance, Nepal and the United States have both agreed that an additional year is necessary to complete the MCC projects. The Nepal government will now formally submit a request for the extension to the MCC Board. The proposal is expected to be considered at the Board's meeting scheduled for December.

Projects financed under the MCC grant are required to be completed within five years from the date the compact comes into force. In Nepal, the agreement became effective on August 30, 2023, meaning the projects are scheduled to be completed by August 2028. Failure to complete the work within the stipulated period could result in the remaining US grant funds being returned.

Several factors have contributed to delays in project implementation. Following US President Donald Trump's return to power in January 2025, the US government initiated a review of foreign assistance programmes, which affected work on the MCC projects in Nepal for nearly seven months. Construction activities were also disrupted by severe flooding in the Trishuli River last year and floods this year.

During the visit of Nepal's Finance Minister Dr Swarnim Wagle to the United States, the issue was discussed with MCC Acting Vice-President Jason Small. Both sides deliberated on the possibility of extending the project timeline to ensure successful completion. Meanwhile, MCA-Nepal had submitted a proposal seeking an extension to the Ministry of Finance, which subsequently placed the matter before the Cabinet.

The grant agreement worth $500 million between the Nepal government and the MCC was signed on September 14, 2017. The US government subsequently added another $50 million to the grant, taking its total contribution to $550 million.

Initially, the Nepal government had committed to contributing $130 million towards the project. Following an increase in project costs, Nepal decided in May 2023 to invest an additional $67 million. This brought the total project cost to $747 million, comprising $550 million in US assistance and $197 million from the Nepal government.

The project involves the construction and improvement of electricity transmission lines, substations and road infrastructure.

Under the MCC Compact, the construction of an 18-kilometre transmission line from the New Butwal Substation to the Indian border has been completed. MCA-Nepal completed the work within nine months of the groundbreaking ceremony. Construction was completed on September 13.

Contracts have also been awarded for the construction of a 297-kilometre transmission line and three substations. Substations with a capacity of 400 kV are being developed in Damauli in Tanahun, Ratmate in Nuwakot and Nawalparasi.

Similarly, a contract has been awarded for upgrading the road along the East-West Highway in Dang, covering the stretch from Dhankhet to Lamahi.

Under the MCC project, tenders for the construction of a total of 315 kilometres of transmission lines were floated three years ago. However, even the lowest bids were 60 per cent higher than the estimated cost, prompting the cancellation of all tenders on October 13, 2023.

Following a subsequent review of the project, the earlier budget was found to be insufficient. The US Congress then provided an additional grant of $50 million. Under the revised arrangement, a separate tender was floated for the 18-kilometre transmission line, while the remaining 297 kilometres of construction were divided into three packages, for which contracts have been awarded.

Although contracts were awarded during the second round of the bidding process, the construction timelines extend beyond the stipulated duration of the MCC Compact. Consequently, extending the agreement's term has become necessary to complete the projects.

It is noteworthy that Nepal's Parliament ratified the MCC agreement on February 27, 2022, following a prolonged political controversy, with an interpretative declaration. The agreement came into force on August 30, 2023, nearly six years after it was signed.

In March 2025, while the US government was continuing its review of foreign assistance, it allowed the MCC to proceed with certain critical procurement processes and office-related operations. In the last week of July 2025, the US government recommended that the MCC project in Nepal continue. The final decision on the proposed one-year extension to ensure the timely completion of the project now rests with the MCC Board.

---------------

Hindusthan Samachar / Jun Sarkar